PMP question 444 discussion

answered

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays.
What should be the concern?

  • A. There is a cost underrun.
  • B. There is a cost overrun.
  • C. The project may not meet the deadline.
  • D. The project is 20 days behind schedule.
Created 1 month, 2 weeks ago by esmaili